Project: Water Rehabilitation Project for Ekiti State

Assignment Name
Country
Water Rehabilitation Project for Ekiti State
Nigeria
Location within Country
Professional staff provided by your firm
Ekiti State
8
Name of Client Number of Staff
Federal Government of Nigeria and Ekiti State Water Corporation
57
Address Number of staff months/Project Duration
PMB 5350
Ado-Ekiti
Ekiti State
1539
Start Date Completion Date Approx. Value of services in Current US$
1999
2000
$530,809.30
Name of Associated Consultants If anyNumber of months of professional staff provided by associated consultants
Ace Lucas and Partners
1
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
  • Project Director/Coordinator: K.G. Till, P.Eng.,
  • Project Coordinator: John Rowe,
  • Project Engineer: Faisal Mirza,
  • Project Coordinator: Mike Whiting
  • Enumeration Team Leader: Sule Olatoye Ojo
Narrative Description of Project
Provision of Technical Consulting Services for improvement of water supply system for various towns and cities in Ekiti State in Nigeria.
Description of actual services provided by your staff

Work included implementation, co-ordination and monitoring of Customer Enumeration and Mapping and a Water Audit/Tariff Study as well as preparation of Operation and Maintenance Manuals.

The project included the aerial photography of 4 large towns in Ekiti State and preparation of mapping for those towns. The project located water mains and developed system mapping from both the site investigations and the available mapping from the Water Corporations Office.